UPDATE: Supreme Court dismisses B.C.’s appeal in Trans Mountain pipeline case

Judges decide whether B.C.’s power to protect environment can include impeding a federal project

The Supreme Court of Canada has shut down B.C.’s attempt to regulate what can flow through an expanded Trans Mountain pipeline from Alberta.

The B.C. government wanted to require provincial permits before heavy oil could be shipped through pipelines in the province.

In 2018, it asked the B.C. Court of Appeal if such permits were in bounds. Last May that court said no, ruling they would violate Ottawa’s authority under the Constitution to approve and regulate any pipeline that crosses a provincial border.

On Thursday, the Supreme Court agreed.

“We are all of the view to dismiss the appeal for the unanimous reasons of the Court of Appeal for British Columbia,” Chief Justice Richard Wagner said.

The decision was issued from the bench after several hours of hearings Thursday in Ottawa.

It removes one of the remaining obstacles for the Trans Mountain pipeline expansion, which seeks to twin an existing pipeline running between Edmonton and Burnaby, B.C.

The twinned pipeline, with roughly twice the capacity of the original, would carry only diluted bitumen, a heavy crude produced in Alberta’s oilsands. The existing pipeline is to continue to ship mainly refined petroleum products like gasoline, and light crude.

Canada’s Natural Resources Minister Seamus O’Regan welcomed the ruling.

“It is a core responsibility of the federal government to help get Canada’s resources to market and support good, middle-class jobs,” he said in a statement.

“We know this is only possible when we earn public trust and work to address environmental, Indigenous peoples’ and local concerns, which we are doing every step of the way on TMX.”

READ MORE: What is being argued when it comes to the Trans Mountain pipeline

Federal lawyers argued B.C.’s attempt to require provincial permits for heavy oil to flow through pipelines was a clear imposition on the constitutional authority given to Ottawa over interprovincial pipelines.

Several of the judges on the Supreme Court agreed in their statements and questions throughout Thursday’s hearing, before issuing their quick dismissal.

B.C’s New Democrat government was elected in 2017 partly on a promise to oppose the expansion but the province had limited options because of the Constitution.

Still, B.C. argued it has jurisdiction to protect the environment within its borders and, since its land and people would bear the brunt of any damage from a spill if the pipeline ruptured, it should get a say in what can flow through it.

B.C. Premier John Horgan expressed the province’s disappointment in a statement.

“Our government takes our responsibility to defend the interests of British Columbians seriously” he said. “When it comes to protecting our coast, our environment and our economy, we will continue do all we can within our jurisdiction.”

The case had national implications for any project that crosses provincial boundaries, prompting Alberta, Saskatchewan, Ontario and Quebec to all seek intervener status. All but Quebec sided entirely with the federal government.

Alberta Premier Jason Kenney took immediately to Twitter to express gratitude for the court decision.

“We are very pleased with this outcome and look forward to construction continuing on the Trans Mountain Pipeline,” he wrote.

Ecojustice, an environmental law charity, also received intervener status in the case. Lawyer Kegan Pepper-Smith said the court’s decision will leave “communities and the environment vulnerable to toxic diluted bitumen spills.”

“Ecojustice is also deeply concerned that the court refused to confirm that governments at all levels have both a right and a constitutional duty to protect the environment,” he said.

This case was the catalyst that led to the federal government’s decision to buy the existing pipeline in May 2018 for $4.5 billion from Kinder Morgan Canada. The company said the political risk that the project would never get built was too much to bear and was planning to halt the expansion.

The federal Liberals argue the pipeline is needed to get more Canadian oil to foreign markets beyond the United States and bought the existing pipeline with a view to completing the expansion once the legal and political challenges were out of the way.

It intends to sell it back to the private sector after the expansion is complete.

Mia Rabson, The Canadian Press

Like us on Facebook and follow us on Twitter.

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

B.C. firefighters only responding to most life-threatening calls during COVID-19 pandemic

The directive comes after province spoke with paramedics, fire services, according to top doctor

Two inmates found positive for COVID-19 at Mission Institution; two other tests pending

15 staff self-isolating waiting results, says correctional officer

‘An extra $220 every 90 days’: B.C. patients pay more dispensing fees due to prescription limits

Kelowna woman says it’s outrageous to charge for refills every 30 days

COLUMN: The other graph that shows B.C. can beat COVID-19

Is the curve being flattened? data on hospitalizations provides a crucial answer.

Goose in Abbotsford rescued after legs wrapped up in fishing line

Wildlife centre operator says people need to be more careful

‘Better days will return’: Queen Elizabeth delivers message amid COVID-19 pandemic

The Queen said crisis reminds her of her first address during World War II in 1940

Emergency aid portal opens Monday, cash could be in bank accounts by end of week: Trudeau

Emergency benefit will provide $2,000 a month for those who have lost their income due to COVID-19

Education, not enforcement: B.C. bylaw officers keeping a watch on physical distancing

A kind word, it turns out, has usually been all people need to hear

COVID-19: Hospitals remain safe for childbirth, say Vancouver Island care providers

North Island Hospital has been asked to share its perinatal COVID-19 response plan

Canadian cadets to mark 103rd anniversary of Vimy Ridge April 9 virtually

Idea of Captain Billie Sheridan in Williams Lake, B.C. who wondered what to do in times of COVID-19

Insurance shock for B.C. condo owners

Claim-free two-year-old townhouse complex told premium will nearly triple

B.C. VIEWS: Pandemic shows need for adequate care home staffing

Seniors in B.C. care homes face challenging times

QUIZ: How much do you know about hockey?

Take this test and find out how well you know Canada’s most popular winter sport

Most Read