The Pattullo Bridge is living on borrowed time. TransLink has concluded it can't be seismically upgraded and should get only minimal repairs until a new bridge can be built.

Pattullo Bridge seismic work scrapped as ‘cost-prohibitive’

TransLink opts to minimize rehabilitation strategy on 80-year-old span, push for new bridge instead (WITH VIDEO)



TransLink is abandoning most of its plan to rehabilitate the 80-year-old Pattullo Bridge and will instead do minimal repairs in hopes a replacement bridge can be built as soon as possible.

It was to start a two-year $100-million upgrade next spring to replace the bridge deck and perform the first phase of seismic strengthening.

But TransLink officials have been warned the seismic portion now looks much more challenging, with a price tag that was set to soar, if it could be done at all.

“It’s cost-prohibitive,” TransLink infrastructure management and engineering vice-president Fred Cummings said Friday.

“We can’t continue to spend money because we don’t have a technical solution to extend the life of the bridge.”

TransLink will proceed to replace the bridge deck with a concrete one and shelve the multi-phase seismic work.

It will mean less short-term disruption for drivers.

Work is expected to take place over about five months next summer, instead of 18 months, and TransLink expects to keep two lanes open at all times, without any of the complete bridge closures previously forecast.

The bridge, which is 30 years past its 50-year design life, remains vulnerable to being knocked out of service by a moderate earthquake, river erosion or a ship collision.

How long the existing Pattullo can stay in service before it must be closed is uncertain.

“On the outside, probably 10 years,” Cummings estimated, adding it depends how rapidly the bridge deteriorates.

TransLink staff monitor it daily and conduct detailed weekly inspections.

He said it’s urgent to solve the question of how to pay for the Pattullo replacement as soon as possible.

The bridge replacement was one of the projects that would have immediately advanced had voters not rejected a 0.5 per cent sales tax increase to fund transportation in this year’s plebiscite.

But many observers expected the new bridge would get built regardless of the vote.

Tolls are expected to cover much of the region’s share of the $1-billion cost of the new Pattullo, with one-third each coming from the provincial and federal governments, but there’s still a $90 million expected shortfall in toll revenue over 10 years that must come from somewhere else.

TransLink officials say chopping the rehabilitation spending from $100 million down to $25 million means the other $75 million can be put towards the replacement project.

Even if the remaining funding is quickly found, the earliest a new bridge could be open is five years – after two years of design and procurement, and three years of construction.

The change in the Pattullo strategy was outlined in a presentation to the TransLink board, in its first open public meeting since promising to end its policy of making all decisions behind closed doors.

The Pattullo Bridge is living on borrowed time. TransLink has concluded it can’t be seismically upgraded and should get only minimal repairs until a new bridge can be built. Black Press file

Just Posted

Abbotsford Panthers celebrate 35th anniversary of title with win

Panthers come from behind to defeat Notre Dame, Mouat edges Bateman in exhibition action

Two parks left in contest to crown Abbotsford’s favourite; Round 4 bracket results

After four rounds, one park chosen to face-off against Mill Lake Park in final

Vehicle accident on Sumas and South Fraser Way intersection

Southbound traffic on Sumas Way slow as the right lane is blocked

New wine patios clear hurdle in Abbotsford

Ripples Winery and Maan Farms Estate Winery each hope to create patios for drinkers

Abbotsford police searching for missing local man

David Cole’s family have not heard from him since early September

VIDEO: Drone footage documents work to free salmon at Big Bar landslide

Video shows crews working to remove rocks and wood, and transporting salmon by helicopter

Defense says burden of proof not met in double murder case against Victoria father

Closing statements begin in trial for man accused of killing daughters Christmas 2017

B.C. dog breeder banned again after 46 dogs seized

The SPCA seized the animals from Terry Baker, 66, in February 2018

Surrey mom allegedly paid $400,000 for son in U.S. college bribery scam

Xiaoning Sui, 48, was arrested in Spain on Monday night

Three dogs found shot dead in Prince George ditch

The three adult dogs appeared to be well cared for before being found with gunshot wounds, BC SPCA says

Vancouver police could be using drones to fight crime by end of year

The police department has already purchased three drones, as well as three others for training

B.C. party bus company to be monitored after 40 intoxicated teens found onboard

Police received tip teens and young adults were drinking on party buses and limousines in Surrey

Grand opening of Molson Coors Fraser Valley Brewery at Chilliwack cause for celebration

Ribbon-cutting with dignitaries, Molson brass and family marked the official grand opening

B.C. cabinet minister denies that Surrey mayor’s friend attended government meeting

Surrey councillor questions Vancouver businessman Bob Cheema’s involvement in official meeting

Most Read