The Site C Dam location is seen along the Peace River in Fort St. John, B.C., on April 18, 2017. THE CANADIAN PRESS/Jonathan Hayward

The Site C Dam location is seen along the Peace River in Fort St. John, B.C., on April 18, 2017. THE CANADIAN PRESS/Jonathan Hayward

First Nation calls for release of Site C report in open letter to premier

The letter says BC Hydro has withheld its two latest progress reports from regulators

A First Nations leader is calling on the British Columbia government to release several reports on the Site C dam, claiming details of escalating costs and safety concerns have been “shrouded in secrecy.”

In an open letter to Premier John Horgan, Chief Roland Willson of the West Moberly First Nations says work on the hydroelectric dam in northeastern B.C. should be suspended immediately until cabinet makes a decision on the project.

“You can reject the madness of ploughing ahead with this unnecessary, unsafe, and unlawful project. You can choose instead to immediately suspend the project,” the letter says.

The letter says BC Hydro has withheld its two latest progress reports from regulators and the premier has refused to release a report prepared by special adviser Peter Milburn.

Although BC Hydro initially said the reports were commissioned by the government and referred comment to the province, it later clarified that the progress reports are its responsibility.

The Crown corporation said in a statement it is undergoing a re-baselining process for the project and will file its next progress report with the B.C. Utilities Commission after that is complete.

The Energy Ministry said in a statement it is reviewing Milburn’s advice and “will share the findings as soon as possible.”

In addition, government is awaiting a report from two independent international experts who are reviewing the measures proposed to address geotechnical challenges at Site C, the ministry said.

The ministry did not respond directly to questions about whether it would pause the project or respond to allegations that the project infringes on the First Nation’s treaty rights.

Willson said in an interview if the reports aren’t made public voluntarily, the First Nation will seek their release through court action.

The First Nation has already prepared a notice of application and served the parties with a motion but is awaiting scheduling availability before filing the document with the court, said Tim Thielmann, a lawyer for the First Nation.

If the documents reveal significant safety risks, costs or scheduling implications, the First Nation may apply for a second injunction against the project. When the B.C. Supreme Court denied an injunction in October 2018, it said a new injunction could be granted if there was “unforeseen and compelling change in circumstances,” he said.

“If we find out that there is a serious safety risk or financial implication that justifies another injunction, then the court has left the door open for West Moberly to bring a new injunction,” Thielmann said.

Soon after taking power, Horgan announced in December 2017 that the government would support completion of Site C, but said it is a project the NDP would never have started.

BC Hydro reported to the B.C. Utilities Commission in July that geotechnical problems found in late 2019 had created a “project risk,” requiring stability measures to be taken on the right bank of the dam.

The B.C. government appointed Milburn, a former deputy finance minister, in July to review the project. Energy Minister Bruce Ralston said this month he wouldn’t discuss its findings until they are reviewed by the premier and cabinet.

Willson said in an interview that the hydroelectric dam is an unnecessary infringement of the First Nation’s treaty rights and he doesn’t believe the community’s concerns have been taken seriously.

“It’s a shame we’re at this stage. We should have never gotten this far down the road. We should have sat at the table like adults,” Willson said.

The Peace River, where the dam will sit, runs through the heart of the First Nation’s territory, Willson said.

“We’re sitting here watching our valley get ripped apart,” he said. “Our spiritual areas are getting destroyed, our burial sites along the river are getting destroyed.”

Treaty members still live near the site and work should be halted if there are real safety concerns, he said.

Given the government’s stated commitment to the United Nations Declaration on the Rights of Indigenous Peoples, Willson said he’s disappointed the government is allowing the project to forge ahead.

The First Nation has already asked the government to share the reports but decided to pen the open letter after hearing no response, he said.

“It’s ridiculous. We’re in an age of reconciliation. We wanted to sit down with them and have a conversation with them about how we can meet the energy needs of B.C. without flooding the valley,” Willson said.

“We want to give them a chance to do the right thing.”

BC Hydro said in a statement that since 2007, it has undertaken extensive and meaningful consultation and engagement with First Nations on Site C and reached benefits agreements with the majority of Treaty 8 First Nations that have been affected by the project.

“We’re committed to working with Indigenous communities and building relationships that respect their interests,” it said.

The project is designed to the highest recommendations of the Canadian Dam Association, it said.

“Safety has been — and will always be — our key priority.”

The Canadian Press

Like us on Facebook and follow us on Twitter.

Want to support local journalism? Make a donation here.

Site C

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

Elias Pettersson and the Vancouver Canucks drew a large crowd to the Abbotsford Centre in 2019. Canucks management hopes the crowds return for the planned AHL team this fall, and early returns are positive. (John Morrow/Abbotsford News)
Canucks: ‘Incredible’ early interest for Abbotsford AHL tickets

Team has had a strong response to both e-mail information and priority ticket lists

Red dot shows location where fisherman was rescued by boater on Friday, May 7, 2021. Other fisher still missing presumed drowned after boat swamped on Fraser River near Vedder/Sumas confluence. Rescued man swam to shore after boat sank, while friend is still classified as missing as of May 10. (City of Chilliwack map)
Fisherman still missing after boat flipped on the Fraser River

One man made it out, other still missing, after anchor got snagged in the Fraser near Chilliwack

Corina Rochon has been working the front lines of the pandemic in the intensive care unit at Abbotsford Regional Hospital. She is also an instructor in the nursing program at University of the Fraser Valley.
Pandemic the most challenging of Abbotsford nurse’s 16-year career

Corina Rochon works front lines at Abbotsford Regional Hospital

Joan Septembre went for a weekend hike at Lindeman Lake, parking next to a vehicle that had two windows smashed in. (submitted photo)
Thieves active at Lindeman Lake and other parking spots along Chilliwack Lake Road

The hiking community is lamenting an uptick in car theft and vandalism as the weather gets nicer

Dario Lopez comes to the Cascades from Madrid, Spain where he played in very competitive junior leagues. (Dan Kinvig/UFV Athletics)
UFV Cascades sign Spanish basketball talent

High-scoring forward Dario Lopez joins team for 2021-22 season

A bullet hole is seen in the windshield of an RCMP vehicle approximately 4 km from Vancouver International Airport after a one person was killed during a shooting outside the international departures terminal at the airport, in Richmond, B.C., Sunday, May 9, 2021. THE CANADIAN PRESS/Darryl Dyck
Homicide team IDs man in fatal YVR shooting as police grapple with spate of gang violence

Man, 20, charged in separate fatal shooting Burnaby over the weekend

The B.C. legislature went from 85 seats to 87 before the 2017 election, causing a reorganization with curved rows and new desks squeezed in at the back. The next electoral boundary review could see another six seats added. (Black Press files)
B.C. election law could add six seats, remove rural protection

North, Kootenays could lose seats as cities gain more

The Independent Investigations Office of B.C. is investigating the shooting of an Indigenous woman in the Ucluelet First Nation community of Hitacu. (Black Press Media file photo)
B.C. First Nation wants ‘massive change’ after its 3rd police shooting in less than a year

Nuu-chah-nulth woman recovering from gunshot wounds in weekend incident near Ucluelet

Nurse Gurinder Rai, left, administers the Moderna COVID-19 vaccine to Maria Yule at a Fraser Health drive-thru vaccination site, in Coquitlam, B.C., on Wednesday, May 5, 2021. The site is open for vaccinations 11 hours per day to those who have pre-booked an appointment. THE CANADIAN PRESS/Darryl Dyck
COVID vaccine bookings to open for adults 40+, or 18+ in hotspots, across B.C.

Only people who have registered will get their alert to book

Dr. Victoria Lee, CEO of Fraser Health, hosts an update on efforts to contain B.C.’s COVID-19 transmission in Surrey and the Fraser Valley and protect hospitals in the Lower Mainland, May 6, 2021. (B.C. government video)
B.C.’s COVID-19 infection rate slowing, 20 more people die

Deaths include two people in their 40s, two in their 50s

The Canadian Forces Snowbirds are in the Comox Valley for their annual spring training. Photo by Erin Haluschak
Suspected bird strike on Snowbirds plane during training in B.C.

Pilot followed protocols and landed the aircraft on the ground without any problems

Cannabis bought in British Columbia (Ashley Wadhwani/Black Press Media)
Is it time to start thinking about greener ways to package cannabis?

Packaging suppliers are still figuring eco-friendly and affordable packaging options that fit the mandates of Cannabis Regulations

Most Read