This map, from the original 2017 presentation, shows the sewer pipe route under the Fraser River.

Costs double for Mission’s multi-million poop pipeline under the Fraser

Mission looking for more funding sources after project cost doubles

Mission needs to find an additional $15 million in order to complete a sewer line crossing underneath the Fraser River.

That’s in addition to the $7 million in federal and provincial funding that has already been secured for the project.

In March 2017, it was announced that the district would build the Fraser River Sanitary Crossing Siphon, for $8.3 million.

The project was approved under the Government of Canada’s Clean Water and Waste Water Fund. The federal government would provide almost $4.2 million, and the provincial government would provide approximately $2.7 million. The district would just over $1.4 million.

READ: An unwanted fountain of sewage could rise

The total price was an estimated $11 million for the crossing and the land needed on both sides of the river.

Today, that cost has doubled to approximately $22 million.

Mike Younie, Mission’s chief administrative officer, said the project is continuing while the district explores other funding options.

“The status right now is that the land portion is almost complete on both sides of the river.”

Younie said the cost of the land came in much higher than originally anticipated.

“Originally, the project was $11.1 million and, when we went out for the land piece, that came out to $6.6 million.”

That’s almost all of the government funding, without even beginning the underwater pipe crossing.

“We are working through our environmental approvals and we are close to getting those. When we have certainty on those, we will go back to the market for the river crossing piece and see what the cost is to finish off the process,” Younie said.

READ MORE: Mission to build $8.3 million sewer line

It is estimated to be $15 million for the river piece.

“We are actively pursuing options with both levels of government to try and secure more grant funding,”

There are several factors that caused the costs to rise.

“The original estimate was done four years ago, so that’s one of the issues,” Younie said.

He said another factor is timing, noting there was a lot of government money around and competition for contractors was intense, so the price goes up. He also said that other communities are experiencing the same issues on their projects.

“The engineers can do the best job they can when they design something and try to cost it out, based on their experience, but until you go to market, you don’t know the true cost.”

A third factor is the type of work that needs to be done.

“It’s a significant project, but if you look at the scope of it, we are putting a much larger diameter pipe underneath the Fraser River.

“It’s a significant engineering marvel, if you will. The technology to install a pipe like that is – or the equipment around is – limited. There are not a lot of vendors who can provide this service.”

While there may be questions about how the district will finance the project, one thing is certain.

“The project has to happen,” Younie said.

Once all the environmental concerns have been met, construction will begin late this year.

“The work, because of the environmental sensitivity, will have to happen in the winter months so sometime in December to February.”

Until then, the district will try to secure as much outside funding as possible.

Younie said borrowing money to cover the costs could be an option.

Currently, Mission is in very good fiscal shape with a very low level of debt. Younie said they could look at internal borrowing from reserves but only if needed.

About the project:

The new sewer line across the Fraser River will twin the aging, existing line that currently brings all of Mission’s sewage to the JAMES Treatment Plant in Abbotsford for processing.

The current sewer line is constantly under pressure and about one kilometre of it is buried in the sand under the Fraser River. It was constructed in 1983 and is now 36 years old. It is believed that the pipe will reach its capacity in the next few years.

The proposed new project would allow the installation of a pipe from Mission to the JAMES waste water treatment plant, of which 950 metres will be in a dredged trench on the bottom of the Fraser River close to the existing siphon.

The increase in capacity of the sanitary trunk system would allow for further development within Mission and also reduce the environmental risk of the existing pipe.

ALSO: Construction could start soon

Just Posted

Body found after SUV found fully engulfed in flames in Abbotsford field

Integrated Homicide Investigation Team has been called in

PHOTOS: West Coast Christmas Show and Artisan Market at Tradex

Over the past 11 years the show has been attended by over 175,000 visitors

SARA for Women names new executive director

Jennifer Breakspear accepts position after two months as interim ED

The Debaters take on the holidays in live show

Hit CBC Radio show comes to Abbotsford Arts Centre on Nov. 22

Advocate for the homeless receives UFV’s Young Distinguished Alumni Award

Jesse Wegenast of Chilliwack recognized for extensive community work in Abbotsford

Teen with cancer whose viral video urged Canadians to vote has died, uncle tweets

Maddison Yetman had been looking forward to voting in her first federal election since junior high school

Security camera records hatchet attack on Langley store owner

Target escaped uninjured, but was ‘upset’ by incident

PHOTOS: Snoozing seal pup captures attention at White Rock Pier

Dozens of seals spent the day at White Rock’s iconic structure

VIDEO: Collision in Surrey breaks axle off SUV

Two people were reportedly sent to hospital

Rowing Canada, UVic investigate celebrated coach for harassment, abuse

Lily Copeland says she felt intimidated and trapped by Williams

Cleanup in the works after tanker truck fire leads to oil spill in B.C.’s Peace region

The province said the majority of the spilled oil likely burned away in the fire.

BC VIEWS: Action needed on healthcare workplace violence

While we’ve been talking about it, the number of B.C. victims has only grown

VIDEO: Vancouver Giants blank Cougars 4-0

Goaltender David Tendeck turned aside all 38 Prince George shots for his WHL-leading third shutout

Most Read