UPDATE: Parties square off over Site C delays

Rushed report unable to determine if dam on $8.8 billion budget

The NDP government’s deadline to deliver a preliminary report on B.C. Hydro’s Site C dam project didn’t allow time to determine if the most expensive construction job in B.C. history is on budget.

Energy Minister Michelle Mungall faced questions in the legislature Thursday about the government-ordered review with a Sept. 20 deadline for a preliminary report, an extra set of public hearings and a final report by Nov. 1. That report will form the basis for the government’s decision on whether to temporarily stop work on the project, proceed with construction or halt the project and remediate the site on the Peace River near Fort St. John.

Peace River South MLA Mike Bernier called on Mungall to assure the 2,600 workers on the project that their jobs are safe as winter approaches. Mungall fired back that the expert review by the B.C. Utilities Commission is a step the B.C. Liberals refused to take, and that is why it is being taken now.

The BCUC released the report ordered by Premier John Horgan’s cabinet late Wednesday evening, hours before a midnight deadline. It leaves more questions than answers as the BCUC proceeds to a new round of province-wide public meetings it was also ordered to hold.

The BCUC review panel concluded it didn’t have enough information to answer questions put to it by the government, on an $8.8 billion construction project that has been underway for two years.

“The panel is concerned that the amount spent on the project as of June 30, 2017, $1.8 billion, might not accurately represent the spending that should have happened on the project activities to date,” the report states.


@tomfletcherbc
tfletcher@blackpress.ca

Like us on Facebook and follow us on Twitter.

Just Posted

Large drug bust yields fentanyl and carfentanil

Abbotsford Police launch investigation after spike in overdose deaths

Funding for new child care spaces in Abbotsford

Money will create 125 new spaces at two locations

Pastor’s gift of his own kidney potentially life-altering for churchgoer

Transplant for Abbotsford resident scheduled for next month

Crown appeals stay against Jamie Bacon in Surrey Six killings

B.C.’s prosecution service says judge’s decision reveals ‘errors of law’

Site C dam goes ahead, cost estimate now up to $10.7 billion

Premier John Horgan says Christy Clark left him no other choice

VIDEO: New series takes in-depth look at sexual harassment in B.C.

Black Press takes a hard look at sexual harassment in B.C.

B.C. teacher suspended after explicit images projected to class

Jeffrey Rohin Muthanna had been viewing porn on a school laptop for two years

Man who pledged to give B.C. hockey team millions charged with fraud

Mike Gould has since repaid $8,000 he allegedly owed Cranbrook restaurant, owner says

UPDATED: Byelection lawsuit cost Langley City $27,000

Last-place candidate Serena Oh failed to convince the Supreme Court to hear her case.

Strong economy fuels housing sales in B.C.: report

Economist says demand for houses is being supported by a large number of millennials entering the market

Tequila, hammers and knives: what not to bring on an airplane

Vancouver International Airport staff provide tips on travelling during the holidays

More than 20,000 pounds of garbage removed from riverside homeless camps

Two camps taken down last week on the banks of the Fraser and Chilliwack rivers

New fighter-jet competition to have national ‘economic interest’ requirement

Trudeau government wants to replace Canada’s aging CF-18s with 88 new fighters by as early as 2025

The top-binged shows on Netflix in 2017

Which show did you cheat on your spouse with by watching ahead?

Most Read