Diversion tunnels have been completed to redirect the Peace River during low water this summer and fall, in one of the most critical steps to completing the Site C dam, March 2020. (BC Hydro)

B.C. Hydro’s Site C set back by COVID-19, foundation changes

Peace River diversion still on track for this fall

B.C. Hydro’s plan to have the third dam on the Peace River complete and in service by 2024 has been set back by work scaling down due to COVID-19 restrictions on construction projects, and additional foundation strengthening for the powerhouse and spillway.

In a progress report filed with the B.C. Utilities Commission July 31, B.C. Hydro CEO Chris O’Riley says the Site C project is still on track to divert the Peace River through a pair of tunnels and begin in-river work. But that too has been complicated by geological conditions. The financial impact of the coronavirus delays and additional work will be better known in the fall, O’Riley said.

“Pandemic-related delays will present further cost pressure on the budget,” O’Riley wrote in a letter to BCUC chair David Morton. “As the evolution of the pandemic is uncertain and the date of resolution is unknown, various cost and scheduled impact scenarios continue to be assessed and refined as part of the re-baselining process.”

The incoming NDP government reluctantly decided to carry on with Site C, after former premier Christy Clark vowed to push the project “past the point of no return” before the 2017 B.C. election. In doing so, Premier John Horgan approved an updated cost estimate of $10.7 billion to complete it, an increase of about $1 billion from the initial estimate.

RELATED: Site C dam project carries on under NDP government

RELATED: NDP pays off $1.1B in B.C. Hydro debt, seeks rate cut

RELATED: After losing at every level, West Moberly sues again

Now the combined effects of COVID-19 and a series of problems have pushed the cost up by an amount not yet known. Those issues included changes to the main civil works contract, increased costs of reservoir clearing, power line construction and highway realignment, and first nations treaty infringement claims and an injunction application.

“Towards the end of December 2019, investigations and analysis of geological mapping and monitoring activities completed during construction identified that some foundation enhancements would be required to increase the stability below the powerhouse, spillway and future dam core areas,” O’Riley wrote.

Before the COVID-19 pandemic, Site C was on track for completion by fall 2023 and full service to the B.C. Hydro grid by 2024.


@tomfletcherbc
tfletcher@blackpress.ca

Like us on Facebook and follow us on Twitter.

BC legislatureCoronavirusSite C

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

Abbotsford restaurant fundraiser supports moms and kids in Mexico

Brodeur’s Bistro donates proceeds on Aug. 17 to Casa de Luz charity

POLICE/2020: Street checks by police down in Abbotsford, but no plans to completely end them

Figures show street checks in Abbotsford relatively representative of city’s population

UPDATE: Arrest made in incident in which ‘agitated’ man pulled out knife on 3 people in Abbotsford

Police say 27-year-old man arrested after information received from public

Abbotsford Police warn that water-testing calls are a scam

Fraudulent messages say City of Abbotsford is offering free water-quality tests

Value Village robbed at knifepoint in Mission

Masked man makes off with cash, avoids police K9 units and escapes

STANDING TALL: Forestry workers meet the challenges, remain hopeful

A look at the forest sector in B.C. – and those hoping for the best – amid mill curtailments

Missed rent payments ‘cause of COVID-19? You have until July 2021 to pay up

Each monthly instalment must be paid on the same date the rent is due.

U.S.-Canada pandemic border restrictions extended into September

‘We will continue to keep our communities safe,’ says Public Safety Minister Bill Blair

578 British Columbians currently infected with COVID-19

Seventy-eight new cases confirmed in past 24 hours

WE Charity registers as lobbyist, lays off staff, looking to sell real estate

WE Charity said its financial position has been greatly affected by the COVID-19 pandemic

Conservation seizes fawn illegally kept captive in Vancouver Island home

A Comox Valley resident charged and fined under the Wildlife Act

Pandemic could be driving more parents to get on board with flu shot: study

University of B.C. study gauges willingness for parents to vaccinate children for influenza

Watchdog clears Okanagan RCMP in death of man after arrest over alleged stolen pizzas

The man died in hospital after having difficulty breathing and broken ribs

35,000 doses of fentanyl part of huge Maple Ridge bust

Largest seizure in RCMP detachment’s history included submachine gun, body armour

Most Read